Work is due to commence on 3 August 2009 with an expected duration of seven weeks.
The main section of road involved is a 1km stretch between Ivanhoe Avenue and Carryduff roundabout and the work includes the provision of a shared footway / cycleway.
Due to the heavy volume of traffic on this arterial route there will be unavoidable delays and disruptions during the progress of the works. A carefully programmed works operation together with planned traffic management systems should minimise the inconveniences to residents, local businesses and the travelling public. Roads Service apologises for any inconvenience however it is impossible to do a scheme like this without disruption.
During weekdays, two-way movement of traffic on the Saintfield Road will be maintained at all times, by providing at least one lane in each direction.
For safety reasons no right turn movements, either into or from public roads and private entrances will be permitted within the coned off areas.
On two Sundays towards the end of the contract, it will be necessary to reduce the Saintfield Road to one operational lane for Carryduff-bound traffic. Belfast-bound traffic will be diverted via the B178 Comber Road, A23 Moneyreagh Road, C369 Manse Road and Cairnshill Road. Advance information signs on closures will be displayed and signing of the diversion route will be in place.
It will also be necessary to close the Manse Road, Mealough Road and Baronscourt Road at times as the work progresses and alternative route signing will be in place to assist the travelling public.
Notes to Editors:
1. For further information please contact the Roads Service at 028 90 253208.
2. Media queries to: Emma Flynn Davies, Press Office, Department for Regional Development, 02890 540372. Out of office hours please contact the Duty Press Officer via pager number 07699 715 440 and your call will be returned.