Major maintenance works to start at M3 Motorway Bridge

Thursday, 10 June 2010

Roads Service today announced plans to carry out major maintenance work at M3 Lagan Bridge.

To facilitate the works a series of lane closures will be put in place at weekends beginning on 20 June and continuing until 19 September 2010.  

Mark McPeak, Roads Service’s Project Manager said: Lagan Bridge requires replacement of the bridge joints to ensure its continued high performance in coping with today’s traffic volumes.”

The works operations and traffic management arrangements have been carefully programmed to minimise inconvenience to the travelling public, local residents and businesses however some disruption will be unavoidable.

Mr McPeak said: The work has been scheduled to take advantage of reduced traffic flows at weekends. A diversion route will be signposted during each closure. Some delays will be inevitable and we ask that motorists be patient as these essential works progress.”

The closures will take place in four phases as follows:-

Phase 1 – East Bound:

The mainline of the M3 will be closed East Bound (towards Bangor) from the M2 to the Sydenham Bypass. Nelson Street On-slip to Middlepath Street will remain open.

Dates:

Saturday Night 19 June 20:00 to Monday morning 21 June 06:00

Saturday Night 26 June 20:00 to Monday morning 28 June 06:00

Saturday Night 18 September 20:00 to Monday morning 20 September 06:00

Phase 2 – East Bound:

The slip roads of the M3 will be closed East Bound (towards Bangor) from Nelson Street to Middlepath Street. The mainline of the M3 from the M2 to the Sydenham Bypass will remain open.

Dates:

Saturday Night 3 July 20:00 to Monday morning 5 July 06:00

Saturday Night 24 July 20:00 to Monday morning 26 July 06:00

Saturday Night 31 July 20:00 to Monday morning 2 August 06:00

Phase 3 – West Bound:

The slip roads of the M3 will be closed West Bound (Towards the M2) from Middlepath Street to Nelson Street. The Mainline of the M3 from the Sydenham Bypass to the M2 will remain open.

Dates:

Saturday Night 7 August 20:00 to Monday morning 9 August 06:00

Saturday Night 14 August 20:00 to Monday morning 16 August 06:00

Saturday Night 21 August 20:00 to Monday morning 23 August 06:00

Phase 4 – West Bound:

The Mainline of the M3 will be closed West Bound (Towards the M2) from the Sydenham Bypass to the M2. Middlepath Street On-slip to Nelson Street will remain open.

Dates:

Saturday Night 28 August 20:00 to Monday morning 30 August 06:00

Saturday Night 4 September 20:00 to Monday morning 6 September 06:00

Saturday Night 11 September 20:00 to Monday morning 13 September 06:00

Notes to editors:

  1. The exact dates and times of the M3 closures for the works will depend on weather conditions and scheme progression and therefore could be subject to change.
  2. Details of all the closures and other lane restrictions are available to view on the Traffic Watch website
  3. The works are part of a Design Build Finance Operate (DBFO) contract awarded to Highway Management (City) Ltd in 2006. For further information on the Lagan Bridge Works the public can contact the road operator, Highway Management Maintenance, on 028 90731133
  4. Media queries to: Emma Flynn Davies, Press Office, Department for Regional Development, Tel: 028 9054 0887. Out of office hours please contact the Duty Press Officer